On 24 Jestha 2081 (06 June 2024), Bavari and Mountain Energy Nepal entered into an agreement to remove debris, including stones, gravel, and sand, deposited by floods in the tunnel of the Mristi Khola Hydroelectric Project for the first phase of repair and maintenance. The Mristi Khola Hydroelectric Project, located in Annapurna Rural Municipality-4, Narachyang, Myagdi District, has an installed capacity of 42 MW.
The removal work was successfully completed on 5 Ashoj 2081 (21 September 2024).
For the second phase of repair and maintenance Bavari and Mountain Energy Nepal entered into an agreement on 28 January 2025 (15 Magh 2081) and the work began on 8 February 2025 (26 Magh 2081) and completed on 12 February 2025 (30 Magh 2081).