Mid Hongu Khola A Hydroelectric Project (22 MW)

Hydropower Projects

In collaboration with the main contractor, Makalu Builders and Suppliers Pvt. Ltd., this company successfully completed the construction of a vertical shaft with a diameter of 3.0 meters and a height of 151 meters, as well as a 30.5-meter-long pilot tunnel to surge shaft with a diameter of 3.0 meters, for the Mid Hongu Khola A Hydroelectric Project (22 MW) located in Solukhumbu. The work was finished in half the contracted time, demonstrating exceptional efficiency.

S.N.ParticularsDetails
1Contract Agreement Between Bavari Construction Pvt. Ltd. and Makalu Builders and Suppliers Pvt. Ltd. “The Excavation of Vertical Pressure Shaft” of Mid Hongu Khola ‘A’ Hydroelectric Project and Additional Work order for “The Excavation of Pilot Tunnel to Surge Shaft” of Mid Hongu Khola ‘A’ Hydroelectric Project
2Contract Date26 August 2024 (Vertical Pressure Shaft)
10 November 2024 (Pilot tunnel to Surge Shaft)
3Work descriptionExcavation of 3.0 m dia. 151 m length Vertical Pressure Shaft and 3.0 m dia. 30.5 m length Pilot Tunnel to Surge Shaft.
4Contract Deadline9-Mar-24
5Mobilization Date20-Sep-24
6Work completion 8-Dec-24