Rahughat Hydroelectric Project (40 MW)

Hydropower Projects

Rahuganga Hydropower Limited, a subsidiary of the Nepal Electricity Authority, is developing the 40 MW Rahughat Hydroelectric Project in the Myagdi district. The main civil contractor, Jayprakash Associates, commenced the construction of a 195-meter vertical shaft and a 145-meter inclined pressure shaft (2.6 meters in diameter) on 2nd Magh 2079 (17th January 2023) and completed them on 1st Jestha 2081 (15th May 2024) through dedicated efforts. The Bavari Construction Pvt. Ltd. was involved in the excavation of both Vertical and Inclined Pressure Shaft and completed the work in the weakest possible geology within the stipulated time.

Key Details of the project
S.N.ParticularsDetails
AContract Agreement Between Jai Prakash Associated Limited and Bavari Construction Pvt. Ltd. for “The Excavation of Vertical Pressure Shaft” of Rahughat Hydroelectric Project (40 MW)
Contract Date3-Nov-22
Contract AmountNRs. 2,25,78,195.78 (Excluding VAT)
Work Commencement Date16-Jan-23
Work descriptionExcavation of 2.95 m dia. 195 m Vertical Pressure Shaft.
Work completion 17-Apr-24
BContract Agreement Between Jai Prakash Associated Limited and Bavari Construction Pvt. Ltd. Contract NameContract Agreement Between Jai Prakash Associated Limited and Bavari Construction Pvt. Ltd. for “The Excavation of Inclined Pressure Shaft” of Rahughat Hydroelectric Project (40 MW)
Contract Date19-Jul-23
Contract AmountNRs. 1,25,69,513.83 (Excluding VAT)
Work Commencement Date1-Oct-23
Work descriptionExcavation of 2.6x*2.6 m horseshoe shaped 145 m Inclined Pressure Shaft.
Work completion 31-May-24