Salient Features

The company had signed an agreement with Mathillo Mailun Khola Jalvidhyut Limited on February 20, 2019, for the construction of the main physical structures of the Upper Mailung Khola Hydroelectric Project (14.3 MW). According to the agreement, the work included the construction of the headworks, vertical and horizontal tunnels, and the powerhouse. After completing all the works, Bavari handed over the project to Mathillo Mailun Khola Jalvidhyut Limited on December 31, 2023. The commercial production of electricity from the project began on Magh 28, 2080, and electricity is being transmitted to the national grid. The structures of this project are located at elevations ranging from 1,500 meters to 2,050 meters above sea level.

Project Contract Details
S.N.ParticularsDetails
1Contract NameMain Civil Works Construction of Mathillo Mailung Khola Jalvidhyut Aayojana (14.3 MW)
MMKJA-MCW-2075/76
2Contract Date20-Feb-19
3Substantial work completion date15-Jul-23
4Taking over certificate31-Dec-24
5Contract AmountNrs. 71,67,88,171.72 (Including VAT)
Key Features of Projects
S.N.ParticularsDetails
AHeadworks
Weir: Boulder lined20.80 m x 5 m (LxH)
Undersluice: Gate with stop log; 1 Nos of Bays2.5 m x3.0 m
Trash Passage: Gate with stop log, 1 Nos. of orifice 1.4 m x2.5 m (BxH)
Intake: Side Intake; 2 Nos. of Orifice 2.0 m x 1.3 m (BxH)
Gravel Trap and Gravel Flushing: Surface with hopper shape, 2 Nos. of bays, and 1 flushing culvertHopper 7.87 m x 5 m x 4.61 m (LxBxH)
Culvert: 1m x 1 m ((BxH)
Approach Canal: Free flow rectangular canal; 2 nos. of branches15.48 m x1.1 m x2.72 m (LxBxH)
Settling Basin: Surface with hopper shape, 2 Nos. of Bays, 2 Nos. of Inlet transition, Intermittent size of flushing culvert 60 m x60 m x 5.70 m ((LxBxH)
Length of Inlet Transition: 27.79 m
Flushing Culvert: 1.5 m x1.0 m (BxH)
BTunnel
HRT: Free Flow, Inverted D Shaped 2.8 m x2.8 m (WxH) and 1735.52 m Length.
Forebay: Underground, rectangular 46.0 m x 5.0 m x 8.30 m (upto crown) (LxBxH) Including transition and spillway 1.1m x 1.0 m
Spillway: Inverted D Shaped with trench at the invert180.67 m x2.8 m x2.8 m (LxBxH)
Trench: 180.67 m x1.1 m x1 m (LxBxH)
Connecting Tunnel: Inverted D shaped 60.54 m x 2.5m x2.5 m (LxBxH)
Horizontal Penstock Tunnel: 1,2 and 31. 151.575 m x2.5 m x 2.5 m (LxBxH)
2. 299.89 m x 2.5 m x 2.5 m (LxBxH)
3. 227.47 m x 2.5 m x 2.5 m (LxBxH)
Adit Tunnel: 70.73 m x 2.5 mx 2.5 m (LxBxH)
Vertical Shaft 01: Length: 224.57 m and Dia: 2.25 m
Vertical Shaft 02: Length: 189.97 m and Dia: 2.25 m
CPowerhouse: Surface34.54 m x13.80 m x18.54 m (LxBxH)
DTailrace: Box culvert 34.35 m Length
Total Quantity of work Accomplished by Bavari in the project
S.N.ParticularsQuantity
1Headworks Excavation Quantity
a.Hard Rock Excavation13,692.81 cu.m
b.Boulder and gravel mixed soil4,275.11 cu.m
2Tunnel Excavation Quantity29,635.41 cu.m
3Powerhouse Excavation Quantity
a.Boulder and gravel mixed soil2,689.33 cu.m
b.Hard Rock Excavation19,121.03 cu.m
4Fore poling /spilling rod138 Nos. 25 mm dia. 3 m long
5Rock bolts of Ø20 mm and Ø25 mm varying from 1.5 m to 4.0 m lengt.6,103 Nos.
6Steel Fibre Reinforced Shotcrete (SFRS) from 50 mm to 125 mm thickness972.98 Cu.m
7Plain Shotcrete (PS) From 75 mm to 100 mm thickness76.74 Cu.m
8C15 Concrete1834.84 Cu.m
9C15 Plum Concrete88.28 Cu.m
10C25 Concrete8,086.69 Cu.m
11C 25 Plum Concrete2,098.86 Cu.m
12C35 Concrete57.73 Cu.m
13Reinforcement Works591.78 MT
14Boulder Lining Works (1.5 m)3034.15 Sq.m
15Gabion works2,416.50 Cu.m