Upper Tamor Hydropower Project (285 MW)

Hydropower Projects

On June 25, 2025 (12 Ashad 2082), Bavari Construction Pvt. Ltd. entered into an agreement with Fewa Construction Pvt. Ltd. for the excavation of critical underground structure for the 285 MW Upper Tamor Hydropower Project, owned by Tamor energy Limited.

Scope of work

Construction of a 300-meter Adit tunnel with dimensions of 3.2m*3.5m to facilitate access for the surge shaft excavation

Excavation of a 147- meter long, 17.5- meter diameter surge shaft

Excavation of a 370-meter long, 5.4-meter diameter vertical shaft.

   

Related Projects