Fewa Construction Pvt. Ltd. and Bavari Construction Pvt. Ltd. entered into an agreement for the excavation of Surge Shaft and Vertical Shaft of Upper Tamor Hydropower Project (285 MW) on 12 Ashad 2082. The contract was signed by Manager of Fewa Construction Pvt. Ltd. Mr. Tuk Prasad Bhandari and General Manager of Bavari Construction Pvt. Ltd. Mr. Mahesh Ghimire. The project is scheduled to complete within 20 months from the date of commencement.